  • Survey and studies (completed)

    April-October 2020
  • Preliminary design (current status)

    Through January 2021
  • Final design

    January-April 2021
  • Right-of-way acquisition discussions

    February-July 2021
  • Contractor bid process

    July-August 2021
  • Start of construction

    September 2021
  • Project completion

    December 2021